Hi All


I was wandering if there is anybody on this forum who has had a side return done where you have had to use pile foundations.


We got a quote from a building company quite prominent in the area, where side returns are effectively their bread and butter. The quote was very competitive and we liked the salesman, so we agreed for them to do the work. Only after we had paid our deposit the additional costs starting coming out of the wood work (although not literally ;-)).


We were told a soil sample would need to be done because if we were on a clay soil the foundations would have to be deeper. Er, hello, does this company employ the only people in the trade who don't know that pretty much ALL of London is on clay. Unsurprisingly the soil sample came back telling us it was clay, and the price goes up because we would now need deeper foundations.


Then we are told there is a tree on the boundary with our neighbor which coupled with the clay soil may mean having to do an "engineered" foundation solution. Er, hello, the tree was there when they came round and quoted. Its not a new tree so a bit annoyed they quoted without factoring this in. I guess they thought they'd hook us in to a contract and then tell us and we'd continue the work with them and a far higher price than first agreed, with what we had as contingency effectively spent before any work even started!!


Well, the latest is that we WILL need pile foundations as they got building control in even before we have been granted planning permission, and we were told via EMAIL a week or two back that they are PULLING OUT of the contract as they do not do pile foundations. Can you believe their customer service was to tell us by email that they were pulling out - absolutely disgraceful. The owner, who I have mailed has still not had the manners to call me.


So, we move on and hence the reason for posting. Not to bad mouth the company, which is why I have not named them but to try and find out from you good people if anybody has had pile foundations and can recommend a good builder who may be able to take this work on. Yes, surprisingly the builders we signed a contract with have not recommended anybody.


Please help.


Thanks


Clicka

We had a side return done two years ago and don't recall any particular issues with foundations. Do remember a soil sample though so I guess we were ok.

We used PlusRooms - also specialists and hopefully they are not the ones who have let you down.

We had to have more substantial foundations.

But only at corner points where steels were going to be resting.


Id suggest that you have a structural engineer review your drawings and report on it.

It's far easier getting builders to quote with the engineers drawings and calculations.

And possibly some architects construction specs based on that report.

We had both done, as a result the contract price was what we paid, no overs.


As for the tree, that's usual depending on distance and type of tree.

We had one, but cut it down a year before starting. It was a horrendous laylandi type that was taller than the house.

We had to have pilling foundations done because of a tree/clay. We used a pilling contractor separately contracted from the builders. The builders had to come and clear the ground, ready for the pilling contractors, who then took over the site for two weeks and then handed it back over to the builders to continue. It wasn't fun and it pushed the costs higher, but we would not have met building regs otherwise...

Tree roots can seriously undermine the strength of clay soils, the clay becomes 'desiccated' and unstable, hence the need to pile down to deep depths where the soil conditions are stable. I'm not sure cutting a tree down before helps as the damage has already been done, but a structural engineer would confirm. I'm surprised that an 'all-in-one' company wouldn't be able to overcome such a discovery, as all it needs is a specialist sub-contractor to do the piling work.

The traditional route of using an architect and structural engineer before a builder is employed usually flushes out such potential problems...

Hi,


Have they been paid any fee already?

I'd find out at what stage the piling information was submitted to Building Control and compare it to the date you were first told about it. It is very strange that they have submitted anything to BC prior to having Planning in place. Also, just because Building Control drawings have been approved, does not mean they can not be changed (in agreement with the council) as the project progresses. Although it might be annoying now, hopefully all that has been lost is time and you have had a lucky escape.


The Design and Build company approach is ok (at best) if you don't mind a one size fits all approach to your project. The approach of winning the project with little site assessment/feasibility is common, the price then only goes in one direction. However, you'll be in contract with them (probably a contract they have written or compiled), with little protection and low value added. The advice Red Devil suggests is good, an architect/engineer should be acting on your behalf, managing these issues and saving money where possible.


T23

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Latest Discussions

    • The sites in question though are not comparable to the builders yard by the station and less likely to be granted planning permission for 9 storey buildings. The builders yard fronts on to the railway line on one side and virtually no residential property surrounding on the other sides. The Gibbs & Dandy /Kwikfit and ED trading trading estate are surrounded at close proximity by residential, and in the case of the latter a Grade II building, so there would more stringent height restrictions. Both these sites are tired and sad looking, and in need of development to provide much needed housing.
    • Not sure if this is any help but was initally told to use google chrome as the browser and the code was the reference. However the person at Southwark parking took pity on me and did it for me 
    • I can see how it could've worked 20 or 30 years ago, when you couldn't swing a pool cue in the Foresters without hitting a sparks, a plumber or a chippy, but the area has changed somewhat. I'm not sure people around here have such trade-able skills these days. Have a word with someone in your local and you'll see. People are always going to need their boiler fixed, a damp patch sorted or their dimmer switch dimmed, but I can pretty much guarantee I'm never going need my corporate policy complied with, my social media planned, my data mined, my green transport tsared, my information architected or my analytics analysed. It reminds me of the great DIY con of the mid to late seventies. My Mum bought into it, my Dad didn't. Anyway, my Mum won out and we let the gardener go (he went on to be TV's Timmy Mallett, so that's a warning from history), but my Dad shorted the house out and singed his head when he cut through the flex on his new Black & Decker hedge trimmer. We all laughed, of course, but he got his own back when, because we didn't use a qualified electrician to do things properly, she electrocuted herself when she pulled the back of the plug off her Carmen heated rollers while it was still in the socket. Keep things professional, say 'No!' to this sort of nonsense. We pay people a decent rate of pay because they're specialists at these things. I did once barter my sister's space hopper and roller skates for twenty-odd square foot of crazy paving, though. That was a birthday present my Mum never forgot, and not in a good way.  
    • Thanks both of you. I have also been having the same problem. I emailed the named person on the letter, with no response. I also tried phoning and was transferred to another number which cut me off. I hope they extend the deadline for applying as there are likely to be many people without a permit by the deadline for applying.